Budget for building design and construction projects
A budget is a statement of the amount of money that is available to spend over a period of time, or on a specific thing, such as a building. It may include an outline plan for how that money will be spent, and a breakdown of the items it will be spent on.
The CIOB Code of practice for project management 4th edition, defines a budget as:
'Quantification of resources needed to achieve a task by a set time, within which the task owners are required to work... a budget consists of a financial and/or quantitative statement, prepared and approved prior to a defined period, for the purpose of attaining a given objective for that period.'
Budgets for construction projects help determine what is affordable and should be set as early as possible. It is important that they are based on evidence and are realistic.
The RIBA Plan of Work 2013 defines the project budget as; 'The client’s budget for the project, which may include the construction cost as well as the cost of certain items required post -completion and during the project’s operational use.'
A project budget can be established by:
- Assessment of projected income and expenses through the life of the project.
- Comparison with similar projects.
- Assessment of the funds available.
- Pre-design analysis of requirements.
- Analysis of preliminary design options.
The project budget is set by the client and is distinct from cost plans prepared by a cost consultant which are likely to focus on the construction cost.
The client's total project budget may include:
- The construction cost.
- Land or property acquisition.
- Approvals fees.
- Planning costs (Section 106 Agreement or Community Infrastructure Levy).
- Financing costs.
- Site investigations.
- Fixtures, fittings and equipment.
- The cost of decanting and relocating, including costs associated with moving staff.
- Contracts outside of the main works.
- Insurance.
- Consultant fees.
- Inflation.
- Contingency.
- VAT.
It is common on projects that the project budget and the project brief diverge over time and it is for this reason that careful cost control is important.
It is important that the client makes clear what costs should be monitored by the cost consultant and what will remain within the control of the client organisation.
NB: NRM 1 defines the authorised budget (sometimes referred to as the approved estimate or cost limit) as; 'the maximum expenditure that the employer is prepared to make in relation to the completed building.'
NB: In the case of Riva Properties Ltd & Ors v Foster + Partners Ltd [2017], the Technology and Construction Court (TCC) found that Foster + Partners had been negligent in failing to design a hotel that could be constructed within Riva Properties budget, and then suggesting that it could be value engineered down to the budget after planning permission had been granted. Foster + Partners were held liable for client's costs of £3.6 million in developing the scheme which was almost £100 million over the budget.
Stephen Homer, a partner at Ashfords LLP, the lawyers that acted for Riva Properties said; "This case serves as a warning to designers that they cannot design in a vacuum. Cost and budget is a key constraint and should always be identified and considered when designing any project, even when the provision of cost advice is expressly excluded from the designer’s obligations."
[edit] Related articles on Designing Buildings
- Accounting.
- Approximate quantities cost plan.
- Benchmarking.
- Best value.
- Bills of quantities.
- Business case.
- Business plan.
- Capital.
- Capital allowances.
- Capital costs.
- Capital value.
- Commercial management.
- Contract sum.
- Contract sum analysis.
- Cost.
- Cost certainty.
- Cost consultant.
- Cost control.
- Elemental cost plan.
- Estimate.
- Final account.
- Green budgeting.
- Initial cost appraisals.
- Net Present Value.
- Pre-tender estimate.
- Price certainty.
- Whole-life costs.
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.
Comments
It would be apt to say that the ultimate success of a project manager and the construction company greatly depends on the fact whether their projects are completed on-time and on-budget. Essentially, construction project management is all about keeping track of the
costs at all stages of the project to ensure that you don’t flout the budget considerations.